Maintenance regime redesign at Halvard Energy
A fixed maintenance calendar replaced by a schedule built on the machines' own readings, and argued with by the crews who run it.

−23%
unplanned turbine downtime
How it was measured
Measured as unplanned outage hours per turbine per year, across 34 turbines, against the three preceding years' mean.
Stated this way because a figure without its method is a claim. Ask us for the workings: we will send them.

Measure before you schedule
Six months of failure data before a single interval was changed.

The technicians write the regime
The people on the plant rewrote the intervals; we held the arithmetic.

Publish the run-rate
Unplanned downtime, weekly, on the board, for twelve months after handover.
The challenge
Turbine maintenance ran on a fixed calendar, which meant servicing healthy machines and missing failing ones. The crews knew which turbines were in trouble; the schedule did not ask them.
The approach
Six weeks measuring the maintenance operation where it happened, travel time, tool time, waits for parts. Then a schedule rebuilt around the sensor history and the crews' own judgement, with every moved job carrying the reason it moved. The crews redesigned the shift pattern themselves once they could see the pattern.
The result
Unplanned downtime fell 23% over the following year, and the schedule is now argued with rather than followed.
The engagement, on paper.
Delivery
Where it sat in the method.
Operations & Performance is stage 03 work. Every engagement opens with the audit whichever stage it lands in, and the roadmap from that audit is what priced this one.

“The schedule is argued with now, rather than followed. That is the difference between a tool the floor trusts and one it works around.”